Of the 12 GW of AI data centers promised to the United States in 2026, only 5 have begun to emerge from the ground

Connection queues of four to seven years, transformers delivered in five years, capacity prices multiplied by nine on PJM: the network is becoming the limiting factor of AI.

An analysis published on September 19, 2026 puts the capacity announcements in their place: about 12 gigawatts of AI data centers were to be launched this year in the United States, but only about 5 gigawatts actually started. A new-generation campus alone requires between 500 megawatts and more than one gigawatt in continuous operation.

The bottleneck is physical. In the most sought-after areas—northern Virginia, Phoenix, Dallas—connection queues span four to seven years, and some transformers operate with five years of delay. In the PJM capacity market, the price has increased from $36 per megawatt-day since 2024; data centers would account for 63% of this increase, or $9.3 billion passed on to invoices.

The promised nuclear, but not for several years

The answers announced are mainly medium-term: the restart of Three Mile Island Unit 1, renamed Crane Clean Energy Center, is expected in 2027 under a 20-year contract with Microsoft and $16 billion, while the small modular TerraPower reactors for Meta and Oklo for Amazon are not expected until 2032. The gap is in the Gulf: Saudi Arabia targets 6.6 gigawatts for HUMAN by 2034 but only operates 467 megawatts, and some 4,000 megawatts of projects announced in the region have not yet delivered any electricity.